Westonci.ca is your trusted source for accurate answers to all your questions. Join our community and start learning today! Experience the ease of finding accurate answers to your questions from a knowledgeable community of professionals. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.

Si para construir un muro de contención en 36 días se necesitan 15 obreros, ¿cuántos trabajadores serán necesarios para realizar la misma obra en 27 días?

Sagot :

Final answer:

To find the number of workers needed for a project in a different timeframe, use the formula Workers x Time = Constant Work.


Explanation:

To determine the number of workers needed to complete a project in a different timeframe, we can use the formula:
Workers x Time = Constant Work. This means that the amount of work required to complete the project remains constant.

Applying this formula to the given situation where 15 workers finish the job in 36 days, we have:
15 workers x 36 days = Total work to be done.

Then, to find the number of workers needed for 27 days, we use the constant work amount and the new timeframe, which gives us the number of workers needed.