At Westonci.ca, we make it easy to get the answers you need from a community of informed and experienced contributors. Our platform offers a seamless experience for finding reliable answers from a network of experienced professionals. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.

Which of the following is NOT an owner's role on the project?

A. Establishing the project program
B. Deciding which project delivery method to use
C. Selecting a contract form
D. Scheduling the project


Sagot :

Final answer:

Owners' roles on a project include deciding the project program, selecting a contract form, and scheduling the project.


Explanation:

Deciding the project program involves determining the project's objectives and scope. Selecting a contract form is crucial for outlining legal aspects of the project. Scheduling the project helps in time management and progress tracking.


Learn more about Project management roles here:

https://brainly.com/question/37681389


We appreciate your time. Please come back anytime for the latest information and answers to your questions. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Your questions are important to us at Westonci.ca. Visit again for expert answers and reliable information.