At Westonci.ca, we provide reliable answers to your questions from a community of experts. Start exploring today! Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.

"A manager is trying to decide whether to build a small, medium, or large facility. Demand can be low, average, or high, with the estimated probabilities being 0.25, 0.40, and 0.35, respectively.
A small facility is expected to earn an after-tax net present value of just $18,000 if demand is low. If demand is average, the small facility is expected to earn $75,000; it can be increased to medium size to earn a net present value of $60,000. If demand is high, the small facility is expected to earn $75,000 and can be expanded to medium size to earn $60,000 or to large size to earn $125,000.
A medium-sized facility is expected to lose an estimated $25,000 if demand is low and earn $140,000 if demand is average. If demand is high, the medium-sized facility is expected to earn a net present value of $150,000; it can be expanded to a large size for a net payoff of $145,000.
If a large facility is built and demand is high, earnings are expected to be $220,000. If demand is average for the large facility, the present value is expected to be $125,000; if demand is low, the facility is expected to lose $60,000."

Draw a decision tree for the three options described in the question above. What should management do to achieve the highest expected payoff?



Sagot :

Answer:

Explanation:

To solve this problem, we'll construct a decision tree to visualize the different options and their associated payoffs based on the probabilities of demand being low, average, or high.

Let's denote the options as follows:

- S: Small facility

- M: Medium facility

- L: Large facility

Here's the decision tree:

```

                     / Low (0.25)

                    /

            S ----<---- Average (0.40)

           / \         \

          /   \         \  

     Low /     \ Average \ High

        /       \         \

       /         \         \

  $18,000    $75,000    $75,000

  (S)        (S)        /     \

                        /       \

                  $60,000 (M)  $125,000 (L)

                      (M)       (L)

                     / Low (0.25)

                    /

            M ----<---- Average (0.40)

           / \         \

          /   \         \  

     Low /     \ Average \ High

        /       \         \

       /         \         \

  -$25,000    $140,000   $150,000

    (M)        (M)       /     \

                        /       \

                  $145,000 (L)  $220,000 (L)

                      (L)       (L)

                     / Low (0.25)

                    /

            L ----<---- Average (0.40)

           / \         \

          /   \         \  

     Low /     \ Average \ High

        /       \         \

       /         \         \

  -$60,000   $125,000    $220,000

    (L)        (L)         (L)

```

To achieve the highest expected payoff, management should choose the option with the highest expected value.

Based on the decision tree and the probabilities given:

- Expected payoff for a Small facility: \( 0.25 \times 18000 + 0.40 \times 75000 + 0.35 \times 75000 = 62250 \)

- Expected payoff for a Medium facility: \( 0.25 \times (-25000) + 0.40 \times 140000 + 0.35 \times 150000 = 111750 \)

- Expected payoff for a Large facility: \( 0.25 \times (-60000) + 0.40 \times 125000 + 0.35 \times 220000 = 101500 \)

Thus, management should choose to build a Large facility to achieve the highest expected payoff.

Visit us again for up-to-date and reliable answers. We're always ready to assist you with your informational needs. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Thank you for trusting Westonci.ca. Don't forget to revisit us for more accurate and insightful answers.