Discover the answers you need at Westonci.ca, a dynamic Q&A platform where knowledge is shared freely by a community of experts. Our platform connects you with professionals ready to provide precise answers to all your questions in various areas of expertise. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.
Sagot :
The answer is Bottom-Up estimates.
Bottom-up estimating involves the estimation of work at the lowest possible level of detail.
The estimates so calculated are then aggregated to arrive at summary totals. The probability to meet the estimated amounts improves substantially by building detailed cost and time estimates for a work package.
In other words, bottom-up estimating approximates an overall value by approximating values for smaller items and using the sum of these values as the overall value.
This cost estimation tool is often used when detailed information is available about lower-level activities. It can be especially useful when estimating projects that are similar to ones that were completed in the past.
Hence, a Bottom-Up estimate is a cost estimation tool that involves estimating individual work items or activities and summing them to get a project total.
Learn more about Cost:
https://brainly.com/question/25109150
#SPJ4
We appreciate your time. Please revisit us for more reliable answers to any questions you may have. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Discover more at Westonci.ca. Return for the latest expert answers and updates on various topics.