Welcome to Westonci.ca, your go-to destination for finding answers to all your questions. Join our expert community today! Discover a wealth of knowledge from professionals across various disciplines on our user-friendly Q&A platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

It takes 15 men, 48 days to weed a plot of land. How

plot of land in 16 days, if
mary men can weed the same
kry work at the sametime?


Sagot :

Answer:

it takes 48 days for 15 men to work

it takes 16 days for 15/48*16

the answer is 5 men

Answer:

45 men

Step-by-step explanation:

If you 1/3 the amount of time (from 48 to 16 ) to weed the plot, you will need to TRIPLE the number of men    to     45  men