Welcome to Westonci.ca, your ultimate destination for finding answers to a wide range of questions from experts. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.
Sagot :
Based on the costs given for PCB Corporation, the Variable costs per unit are:
- Variable cost per unit = $10
- Variable cost per unit for utilities = $0.60
- Variable cost per unit for maintenance = $0.30.
What are the variable costs per unit?
The variable cost per unit is:
= (Direct material + Direct labor + Indirect labor) / Units produced
= (7,500 + 18,000 + 4,500) / 3,000
= $10 per unit
The variable cost per unit for utilities is:
= (Total cost of utilities - Fixed portion of utilities cost) / Units produced
= (2,100 - 300) / 3,000
= $0.60
The variable cost per unit for maintenance is:
= (Total cost of maintenance - Fixed portion of maintenance cost) / Units produced
= (1,100 - 200) / 3,000
= $0.30
Find out more on variable cost per unit at https://brainly.com/question/5965421.
#SPJ1

We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Thank you for using Westonci.ca. Come back for more in-depth answers to all your queries.