Westonci.ca offers quick and accurate answers to your questions. Join our community and get the insights you need today. Connect with professionals on our platform to receive accurate answers to your questions quickly and efficiently. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.

An analysis of past maintenance costs indicates that maintenance cost is an average of $0.20 per machine-hour at an activity level of 10,000 machine-hours and $0.25 per machine-hour at an activity level of 8,000 machine-hours. If this activity is within the relevant range, what is the total expected maintenance cost if the activity level is 8,700 machine-hours?

Sagot :

Answer: $2000

Step-by-step explanation:

Variable cost = Change in cost ÷ Activity change

($2000 - $2000) ÷ (10000 - 8000) = $0

Fixed cost element = Final cost - Variable cost

$2000 - ($0.00 ×10000) = $2000

Therefore, the cost formula for total maintenance is $2000 plus $0 per hour

y = $2,000 + $0x

At a level of 8,700 machine-hours, the total cost is:

y = $2000 + ($0.00 ×8700) = $2000

Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Thank you for using Westonci.ca. Come back for more in-depth answers to all your queries.