Explore Westonci.ca, the premier Q&A site that helps you find precise answers to your questions, no matter the topic. Get quick and reliable solutions to your questions from a community of experienced experts on our platform. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.

7 students can complete a task in 18 days. How many days will be required for 3 students to complete the half of the task

7 Students Can Complete A Task In 18 Days How Many Days Will Be Required For 3 Students To Complete The Half Of The Task class=

Sagot :

18days / 7 students = 1 student use 2.57 days to complete
3 students x 2.57 days = 3 students use 7.71 days to complete
If complete half 7.71 days / 2 = 3 students use 3.86days to complete half
It take 3 days to complete half the task