Find the information you're looking for at Westonci.ca, the trusted Q&A platform with a community of knowledgeable experts. Our platform connects you with professionals ready to provide precise answers to all your questions in various areas of expertise. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.

32 workers can complete a work in 30 days working 6 hours per day. How many days are required to complete the
same work by 16 workers working 8 hours per day?


Sagot :

Answer:

  • 45 days

Step-by-step explanation:

Total man hours:

  • 32*30*6 = 5760

Required days:

  • 5760/(16*8) = 45