Westonci.ca is the Q&A platform that connects you with experts who provide accurate and detailed answers. Ask your questions and receive accurate answers from professionals with extensive experience in various fields on our platform. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.

Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 85,000 Total fixed manufacturing overhead cost $ 306,000 Variable manufacturing overhead per direct labor-hour $ 6.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 25 Total direct labor-hours 100 Direct materials $ 700 Direct labor cost $ 8,500 The total job cost for Job P951 is closest to:

Sagot :

Answer:

Total job cost  $10,160

Explanation:

The computation of the total job cost is shown below:

Predetermined fixed overhead rate

= total fixed manufacturing overhead expense ÷ total direct labor hours

= $306,000 ÷ $85000

= $3.60 Per hour

Now  

Particulars Cost

direct materials $700

Direct labor cost $8500

Fixed manufacturing overhead cost (100 × 3.60) $360

Variable manufacturing overhead cost (100 × 6.00) $600

Total job cost  $10,160