At Westonci.ca, we provide clear, reliable answers to all your questions. Join our vibrant community and get the solutions you need. Ask your questions and receive precise answers from experienced professionals across different disciplines. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.

Given the following information, determine the activity rate for setups.

Activity Pool Activity Base Budgeted Amount
Setups 10,000 $180,000
Inspections 24,000 $120,000
Assembly (DLH) 80,000 $400,000

a. $58.00
b. $0.75
c. $5.09
d. $18


Sagot :

Answer:

Set up= $18 per set up

Explanation:

Giving the following information:

Activity Pool Activity Base Budgeted Amount

Setups 10,000 $180,000

To calculate the activity rate, we need to use the following formula:

Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base

Set up= 180,000 / 10,000

Set up= $18 per set up

We hope our answers were useful. Return anytime for more information and answers to any other questions you have. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Westonci.ca is committed to providing accurate answers. Come back soon for more trustworthy information.