Discover answers to your most pressing questions at Westonci.ca, the ultimate Q&A platform that connects you with expert solutions. Get immediate and reliable answers to your questions from a community of experienced professionals on our platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.
Sagot :
Answer and Explanation:
The computation is shown below:
a. The labor rate variance is
= (standard rate - actual rate) × actual labor hours
= ($20 - $19.50) × 64,000
= $32,000 favorable
b. The labor efficiency variance is
= (standard hours - actual hours) × standard rate
= (62,500 - 64,000) × $20
= -$30,000 unfavorable
c. the total flexible budget variance is
= standard cost - actual cost
= ($1,250,000 - $1,248,000)
= $2,000 favorable
Thank you for visiting our platform. We hope you found the answers you were looking for. Come back anytime you need more information. Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Westonci.ca is committed to providing accurate answers. Come back soon for more trustworthy information.