Discover a wealth of knowledge at Westonci.ca, where experts provide answers to your most pressing questions. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

14.With earned value management (EVM), the Government can determine if a program is currently experiencing a/n

Sagot :

Answer: cost or schedule variance

Explanation:

Earned value management, refers to the project management technique that's used for the measurement of project progress and performance.

Earned value management integrates the cost, schedule, and scope in the measurement of project performance and this can be used by the government to determine if a program is currently experiencing a cost or schedule variance.