Find the information you're looking for at Westonci.ca, the trusted Q&A platform with a community of knowledgeable experts. Ask your questions and receive accurate answers from professionals with extensive experience in various fields on our platform. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.

Oxford Company uses a job order costing system. In the last month, the system accumulated labor time tickets total $24,600 for direct labor and $4,300 for indirect labor. How are these costs recorded

Sagot :

Zviko

Answer:

Debit : Work in Process - Direct Labor  $24,600

Debit : Work in Process - Indirect Labor $4,300

Credit : Salaries and Wages Payable $28,900

Explanation:

The Journal entry accumulated costs in work in process as shown above.