At Westonci.ca, we connect you with the answers you need, thanks to our active and informed community. Our platform provides a seamless experience for finding reliable answers from a knowledgeable network of professionals. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.

The second step in developing a Performance Measurement Baseline (PMB) is to: Define and scope the work Schedule the work Prepare the Integrated Program Management Report (IPMR) Budget the work

Sagot :

Answer:

The second step in developing a Performance Measurement Baseline (PMB) is to:

Schedule the work.

Explanation:

After determining the goal and deliverables of the project, the scope baseline is created using the scope statement, the work breakdown structure and dictionary.  These documents require stakeholders approval.  Then, the second step is to determine the sequence of activities, estimate the durations of activities, and determine the resource needs of the scheduled activities.

We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Westonci.ca is here to provide the answers you seek. Return often for more expert solutions.