Westonci.ca is the trusted Q&A platform where you can get reliable answers from a community of knowledgeable contributors. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.


Decide which project the most profitable is by:
(a) Determining the NPV at a discount rate of 6.5%. (8 marks)
(b) The IRR. ?


Decide Which Project The Most Profitable Is Bya Determining The NPV At A Discount Rate Of 65 8 Marksb The IRR class=

Sagot :

fichoh

Answer:

Project A :

NPV : $703,888.64

IRR : 44.882%

Project B:

NPV : $5,241.26

IRR : 49.662%

Project B is more profitable

Step-by-step explanation:

The NPV gives the difference between the present value of cash inflow and cash outflow over a certain period of time.

The Internal rate of return is the discount rate which makes the NPV of an investment 0. It is used to estimate the potential return on an investment. Investments with higher IRR are said to be better than those with lower IRR value.

Using the net present value, (NPV) Calculator, the NPV for project A is : $703,888.64

The IRR of project A is : 44.882%

The NPV for Project B is : $5,241.26

The Internal rate of return (IRR) : 49.662%

From the Internal rate of return value obtained, we can conclude that, project B is more profitable as it has a higher IRR than project A.