Westonci.ca is the premier destination for reliable answers to your questions, provided by a community of experts. Discover the answers you need from a community of experts ready to help you with their knowledge and experience in various fields. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

thirty-six men can paint a shopping mall in 25 days. How many days will it take 15 men to paint the mall, if they work at a same rate?​

Sagot :

Answer:

12.5 days

Step-by-step explanation:

Given

No of workers= 30

Time taken to paint shopping mall= 25 days

Assume time taken for 15 men =X

Time taken for 15men to paint X= (15*25)/30

=12.5 days