Discover a world of knowledge at Westonci.ca, where experts and enthusiasts come together to answer your questions. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.
Sagot :
Answer:
Project X = $6,980.82
Project Y = - $2,478.42
Explanation:
The Present value is the price today of future cash flows and is calculated as follows :
Project X
($21,000) CF 0
$8,000 CF 1
$8,000 CF 2
$8,000 CF 3
$8,000 CF 4
$8,000 CF 5
$8,000 CF 6
I/YR = 18%
Therefore, NPV is $6,980.82
Project Y
($21,000) CF 0
$0 CF 1
$0 CF 2
$0 CF 3
$0 CF 4
$0 CF 5
$50,000 CF 6
I/YR = 18%
Therefore, NPV is - $2,478.42
We appreciate your time. Please come back anytime for the latest information and answers to your questions. We appreciate your time. Please come back anytime for the latest information and answers to your questions. We're glad you chose Westonci.ca. Revisit us for updated answers from our knowledgeable team.