Westonci.ca connects you with experts who provide insightful answers to your questions. Join us today and start learning! Our Q&A platform offers a seamless experience for finding reliable answers from experts in various disciplines. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.
Sagot :
Answer: See explanation
Explanation:
From the information given,
Budgeted hours = 660
Budgeted rate per hour = 3.4
Budgeted rooms to clean = (600 × 60)/36 = 36000/36 = 1000
1. What is the amount of the budget variance?
This will be:
= (Actual room - Budgeted room) × Standard rate
= (1050 - 1000) × 3.4
= 50 × 3.4
= 170 favorable
2. What is the amount of the volume variance?
This will be:
= Standard cost - Actual labor cost
= (630 × 3.4) - (660 × 3.3)
= 2142 - 2178
= 36 Unfavorable
3. What is the amount of the efficiency variance?
This will be:
= 3.4 × (630 - 660)
= 3.4 × (-30)
= 10.20 Unfavorable
4. What is the amount of the rate variance?
This will be:
= Actual time ( Standard rate - Actual rate)
= 660 × (3.4 - 3.3)
= 660 × 1
= 660 Favorable
Thank you for trusting us with your questions. We're here to help you find accurate answers quickly and efficiently. Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.