Westonci.ca is the best place to get answers to your questions, provided by a community of experienced and knowledgeable experts. Get quick and reliable solutions to your questions from a community of experienced experts on our platform. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.
Sagot :
Answer:
Cherokee Manufacturing Company
a. Sales volume variance is:
= $2,400 F
b. Variable cost volume variance is:
= $1,440 U
c. Fixed cost in the flexible budget = $4,800
d. Fixed cost per unit:
1. Planned activity = $2.40
2. Actual activity = $2.18
Explanation:
a) Data and Calculations:
Standard price and cost data:
Sales price $ 12.00 per unit
Variable manufacturing cost $ 7.20 per unit
Fixed manufacturing cost $ 3,600 total
Fixed selling and administrative cost $ 1,200 total
Planned production and sales = 2,000 units
Actual production and sales = 2,200 units
Sales volume variance = Actual sales - Standard sales multiplied by Standard price
= 2,200 - 2,000 * $12
= 200 * $12
= $2,400 F
Variable cost volume = Actual production - Standard production multiplied by Standard Variable Cost
= 200 * $7.20
= $1,440 U
Flexible fixed costs:
Fixed manufacturing cost = $ 3,600 total
Fixed selling and administrative cost = $ 1,200 total
Total fixed costs = $4,800
Fixed cost per unit:
Planned activity = $2.40 ($4,800/2,000)
Actual activity = $2.18 ($4,800/2,200)
Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Thank you for your visit. We're committed to providing you with the best information available. Return anytime for more. Thank you for trusting Westonci.ca. Don't forget to revisit us for more accurate and insightful answers.