Westonci.ca is the premier destination for reliable answers to your questions, brought to you by a community of experts. Explore a wealth of knowledge from professionals across various disciplines on our comprehensive Q&A platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.
Sagot :
Answer:
See below
Explanation:
1. The predetermined manufacturing rates
= Estimated yearly overhead cost / Estimated yearly machine hour
Estimated yearly overhead cost = Budgeted manufacturing overheads - Plant utilities + Indirect materials + Plant depreciation + Indirect labor MFR costs
= $71,000 + $900 + $52,000 + $39,500
= $163,400
Estimated yearly machine hour = 6,800
= $163,400/6,800
= $24.03 per machine hour
2. The allocated manufacturing overhead for the past year
= Actual machine hours × Predetermined machine hours
= 6,800 × $24.03
= $163,404
3. Manufacturing overhead
Actual manufacturing overhead = Actual indirect materials + Actual indirect manufacturing labor + Actual depreciation on plant and equipment + Actual plant utilities
= $54,500 + $41,500 + $65,500 + $1,900
= $163,400
Over applied overhead = Actual manufacturing overhead - Applied manufacturing overhead
= $163,400 - $163,404
Over applied overhead = $4
4. Journal entry
Cost of goods sold Dr $4
...................To Over applied manufacturing overhead Cr $4
(Being over applied overhead to cost of goods sold)
We appreciate your time. Please revisit us for more reliable answers to any questions you may have. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.