Get reliable answers to your questions at Westonci.ca, where our knowledgeable community is always ready to help. Find reliable answers to your questions from a wide community of knowledgeable experts on our user-friendly Q&A platform. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.
Sagot :
Answer:
1.03
Explanation:
Activity Amount spent Planned % Planned value
A 22,000 90% $19,800
B 14,000 80% $11,200
C 12,000 70% $8400
D 28,000 20% $5600
Total planned value $45,000
Activity Amount spent Actual percentage Earned value
A 22,000 100% $22,000
B 14,000 90% $12,600
C 12,000 75% $9000
D 28,000 10% $2,800
Total Earned value $46,400
Schedule performance Index = Total Earned value/Total planned Value
Schedule performance Index = 46,400/45,000
Schedule performance Index = 1.03
We hope our answers were helpful. Return anytime for more information and answers to any other questions you may have. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.