Westonci.ca makes finding answers easy, with a community of experts ready to provide you with the information you seek. Get quick and reliable solutions to your questions from a community of experienced experts on our platform. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.
Sagot :
Answer and Explanation:
The computation is shown below:
1. Plant wide overhead rate = Budgeted Overheads ÷ Budgeted Activity.
where,
Budgeted Overheads :
Handling materials 625,000
Inspecting product 900,000
Processing purchase orders 105,000
Paying suppliers 175,000
Insuring the factory 300,000
Designing packaging 75,000
Total Cost 2,180,000
And, the budgeted activity is 125,000
So, Plant wide overhead rate is
= Budgeted Overheads ÷ Budgeted Activity.
= $2,180,000/125,000
= $17.44 per direct labor hour
Now Assignment of Overheads
As Deluxe model required 2,500 direct labor hours
So, Deluxe model = 2,500 × $17.44
= $43,600
As Basic model required 6,000 direct labor hours
So, Basic model = 6,000 × $17.44
= $104,640
We appreciate your time. Please revisit us for more reliable answers to any questions you may have. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. We're glad you visited Westonci.ca. Return anytime for updated answers from our knowledgeable team.