Westonci.ca is the premier destination for reliable answers to your questions, provided by a community of experts. Get detailed answers to your questions from a community of experts dedicated to providing accurate information. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

The WBS is an input for which of the following activities?
A.
Schedule planning and budget planning
B.
Schedule planning and scope planning
MARKET
C. Budget planning and project charter creation
D.
Scope planning and budget planning
Is ?


Sagot :

Lanuel

Answer:

A. Schedule planning and budget planning.

Explanation:

Work Breakdown Structure (WBS) is a tool that the project manager uses to progressively divide deliverables into smaller pieces. It gives framework that can be used as a basis for further planning activities. They are displayed in an indented outline format.

Simply stated, Work Breakdown Structure (WBS) in project management is the laser-focused breakdown of a project into smaller components in order to make the project successful.

Hence, the WBS is an input for schedule planning and budget planning.

This ultimately implies that, the WBS is the starting place for schedule planning and budget (financial) planning, and as a result, it serves as the critical input to various deliverables and processes in project management.