Westonci.ca is your go-to source for answers, with a community ready to provide accurate and timely information. Experience the convenience of getting reliable answers to your questions from a vast network of knowledgeable experts. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

Job costing, accounting for manufacturing overhead, budgeted rates. The Pisano Company uses a job-costing system at its Dover, Delaware, plant. The plant has a machining department and a finishing department. Pisano uses normal costing with two direct-cost categories (direct materials and direct manufacturing labor) and two manufacturing overhead cost pools (the machining department with machine- hours as the allocation base and the finishing department with direct manufacturing labor costs as the allocation base). The 2014 budget for the plant is as follows:

Machining Department Finishing Department
Manufacturing overhead costs $9,065,000 $8,181,000
Direct manufacturing labor costs $970,000 $4,050,000
Direct manufacturing labor-hours 36,000 155,000
Machine-hours 185,000 37,000

Required:
What is the budgeted manufacturing overhead rate in the machining department? In the finishing department?


Sagot :

Zviko

Answer:

Budgeted manufacturing overhead rate in the machining department is $49.00 per machine hour.  In the finishing department is $52.78 per direct labor hour.

Explanation:

Budgeted manufacturing overhead rate = Budgeted Overheads ÷ Budgeted Activity

Note that ;

1. Machining department has machine- hours as the allocation base.

2.Finishing department has direct manufacturing labor costs as the allocation base

Therefore,

Budgeted manufacturing overhead rate (Machining department) = $9,065,000 ÷ 185,000 = $49.00 per machine hour

Budgeted manufacturing overhead rate (Finishing department) = $8,181,000 ÷ 155,000 = $52.78 per direct labor hour

Conclusion

Budgeted manufacturing overhead rate in the machining department is $49.00 per machine hour.  In the finishing department is $52.78 per direct labor hour.