Westonci.ca is the Q&A platform that connects you with experts who provide accurate and detailed answers. Explore our Q&A platform to find reliable answers from a wide range of experts in different fields. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

At Medallion Industries, variable cost per unit is budgeted to be $8.00 and fixed cost per unit is budgeted to be $5.00 in a period when 4,000 units are produced. What is the expected total cost of the units produced at Medallion, if instead, production is actually 5,100 units

Sagot :

Answer:

Total cost= $60,800

Explanation:

Giving the following information:

For 4,000 units:

Unitary variable cost= $8

Unitary fixed cost= $5

First, we need to calculate the total fixed cost:

Total fixed cost= 5*4,000= $20,000

Now, we can determine the total cost for 5,100 units:

Total cost= 5,100*8 + 20,000

Total cost= $60,800

We hope this was helpful. Please come back whenever you need more information or answers to your queries. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Get the answers you need at Westonci.ca. Stay informed with our latest expert advice.