Explore Westonci.ca, the top Q&A platform where your questions are answered by professionals and enthusiasts alike. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.
Sagot :
Answer: 125%
Explanation:
Here's the complete question:
The Work in Process inventory account of a manufacturing company shows a balance of $2,400 at the end of an accounting period. The job cost sheets of the two uncompleted jobsshow charges of $400 and $200 for direct materials, and charges of $300 and $500 for direct labor. From this information, it appears that the company is using a predetermined overhead rate, as a percentage of direct labor costs, of:
A. 80%
B. 125%
C. 300%
D. 240%
First, we have to calculate the overhead cost of the incomplete jobs. This would be:
Ending Work in process balance = $2,400
Less: Direct materials cost of uncompleted Jobs = $600
Less: Direct labor cost of uncompleted Jobs = $800
Therefore, Overhead cost of Uncompleted Jobs = $1,000
Then, the predetermined overhead rate would be calculated as:
= Overhead cost / Direct labor cost of the uncompleted Jobs
= $1000 / $800
= 1.25
= 125% of direct labor cost
Thank you for visiting our platform. We hope you found the answers you were looking for. Come back anytime you need more information. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Westonci.ca is here to provide the answers you seek. Return often for more expert solutions.