At Westonci.ca, we make it easy to get the answers you need from a community of informed and experienced contributors. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.

You manage a development organization. One of your Scrum Teams is continually interrupted by unplanned work related to production incidents for a legacy application unrelated to their product. A few team members have historical knowledge of the legacy application. How should the Scrum Team manage the interruption and unplanned work?

A. The Scrum Team should fit the work in, working overtime if that is what it takes.
B. New development work should be put on hold until the production support work is completed; supporting existing applications is always more important than new work.
C. Work with the Scrum Team to help transfer the knowledge to other teams better aligned with the application support mission.


Sagot :

Thank you for visiting our platform. We hope you found the answers you were looking for. Come back anytime you need more information. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Your questions are important to us at Westonci.ca. Visit again for expert answers and reliable information.