Westonci.ca is your go-to source for answers, with a community ready to provide accurate and timely information. Our platform connects you with professionals ready to provide precise answers to all your questions in various areas of expertise. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,360,000. During 2018, costs of $2,120,000 were incurred with estimated costs of $4,120,000 yet to be incurred. Billings of $2,620,000 were sent, and cash collected was $2,370,000.

In 2019, costs incurred were $2,620,000 with remaining costs estimated to be $3,780,000. 2019 billings were $2,870,000 and $2,595,000 cash was collected. The project was completed in 2020 after additional costs of $3,920,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.

Required:
1. Prepare journal entries to recognize revenue for 2018, 2019 and 2020.