Welcome to Westonci.ca, your go-to destination for finding answers to all your questions. Join our expert community today! Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

an engineering company was awarded a project with an original budget of 160,000 hours, valued at $15,000,000. the client has asked the project to prepare an in-depth analysis of the project performance and make a formal presentation. use the following data to prepare the reports and presentation as requested by the client. planned hours 65,000 actual hours spent to date 73,000 % complete 40% what many hours have the project earned?